Jared Knerr, P.E., P.S.

Licking County Engineer's Office
20 S 2nd St., Newark, OH
3rd Floor
(directions)

Our Mission

The mission of The Licking County Engineer's Office is to provide prompt, courteous service to the public, while fulfilling our obligations set forth by the Laws of Ohio in the most efficient and cost effective manner possible.

 

News And Announcements

UPDATE 8/28/2018:  Planning Continues for Replacement of the Flood Damaged Staddens Bridge Road Bridge in 2019

The 250-foot span over the Licking River at Staddens Bridge Road in eastern Licking County has been closed since April.  Its structural integrity was compromised by flooding and tons of heavy debris that built up against the structure.  Licking County Engineer, Jared Knerr permanently closed the aging and damaged structure as a matter of public safety, and established detour routes. Licking County officials appreciate that this unexpected closure continues to be a major inconvenience to residents and businesses in the region.

     Since the damage this past spring, Engineer Knerr and the Licking County Commissioners have been working toward a replacement project for what is a typically heavily used span.  New and updated geo-technical research is being done at the site, and an engineering and design firm was engaged to plan for a replacement for the Staddens Road Bridge.

     Engineer Knerr confirms that the design and planning for the new bridge is almost complete, with just some final touches and verifications to be added.  The first element of the project will be the demolition of the damaged 43-year old span, as well as removing both current and old pilings, from a previous bridge, from the Licking River channel.

     The most difficult aspect of this replacement project is putting together a financing package which is anticipated to be some $2-million to clear the channel and build the new bridge.  Engineer Knerr and County Commissioner Duane Flowers, Rick Black and Tim Bubb are working on a number of funding options, and possible grants or low interest loans.  The funding effort is a challenging and on-going effort.

     The plan going forward, according to the Engineer and the Commissioners is to put the project out for public bid this winter in anticipation of the 2019 project.  An exact timetable for the bidding process has yet to be established.  As the funding plan is finalized and the bidding conducted, it is anticipated the construction of the new Staddens Bridge Road Bridge will be complete in late 2019. The Commissioners and the Engineer will continue to update the community in the weeks ahead as this emergency bridge  replacement project moves forward.


2018 Paving & Bridge Replacement Program

The County Engineer plans to pave approximately 10.76 miles, chip seal 28.80 miles and replace several bridges throughout Licking County. Please note that the locations may change due to unforeseen circumstances. As start dates are added and/or locations change a new map will be provided. Click here to view the current map

Top